There is progress in the new GPCs. The walls are being painted, the are almost ready for the new ceilings to go in, and chair rail has been installed in some of the rooms! See below for details on each room and pictures of the latest progress!

HOLDEN 033

  • Chalkboard removed
  • Old ceiling removed and almost ready for new one to be installed
  • Walls are being painted
  • Chair rail installed

HOLDEN 038

  • Chalkboards removed
  • Old ceiling removed and almost ready for new one to be installed
  • Wall between rooms 038 & 039 is gone!
  • Old chair rail in 038 has been removed
  • Walls are being painted

HOLDEN 104

  • Desks removed
  • New chair rail installed on the back wall
  • Existing chair rail has been painted
  • Inside of doors have been painted
  • Walls are being painted
  • New concrete poured for extended ADA seating in the center of the room and on the Northeast corner

HOLDEN 155

  • Chalkboards removed
  • Old ceiling removed and almost ready for new one to be installed
  • Chair rail installed
  • Walls and chair rail are being painted

HOLDEN 225

  • Chalkboard has been removed
  • Old ceiling removed and almost ready for new one to be installed
  • Walls are being painted
Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s